HomeMy Public PortalAboutWeek of 0720 Work PlanAnticioated Work —Week of July 20. 2020
• Common Street
o Continue drainage, curb, and sidewalk installation at the Spring Street/Common Street
intersection
o Adjust castings throughout project area
o Top course paving of Orchard Street Extension, Katherine Road, and Columbia Street
scheduled for Wednesday, July 22 and Thursday, July 23 (subject to change)
• Road Program
o Continue driveway forming and pouring on Chandler Street, Burnham Street and
Bridgham Ave.
o Continue forming and pouring sidewalks, accessible ramps, and driveways on Piermont
Street and Tappan Ave.
o As work pace permits, begin stripping sidewalks and curb installation on Bartlett Street
• Complete Streets Project
o Adjust castings on Watertown Street
o Installation of rectangular rapid flashing beacons
o Paving of Watertown Street, Whites Ave. and Linear Park scheduled for Wednesday, July
22 and Thursday, July 23 (subject to change)
• Sewer System Rehabilitation
o No work planned
• Sidewalk Repair
o Continue sidewalks on Emerson Road
o As work pace permits, begin sidewalk repairs in Watertown Square in the vicinity of the
Columbus Delta
• 2020 Water Main Replacement
o Connection of by-pass pending bacteriological testing results
• Line Painting
o Night work throughout Town
• National Grid
o Continue Irving Street gas main relay
o Continue gas main relays on Forest Street
o Continue gas relay on Wheeler Lane at Riverside Ave.
o Continue work on Templeton Parkway at Mt. Auburn Street
o No work on Belmont Street at Duff Street planned
o Note: service connections on all main relays on hold due to COVID-19
Note: All work is weather -dependent and subject to change.