HomeMy Public PortalAboutWeek of 0727 Work PlanAnticioated Work —Week of July 27. 2020
• Common Street
o Adjust curb layout at Common Street/Orchard Street splitter islands
o Begin installation of truck island curbing
• Road Program
o Loam and seed and complete transitions and driveways on Chandler Street, Burnham
Street and Bridgham Ave.
o Loam and seed and complete transitions and driveways on Piermont Street and Tappan
Ave.
o Begin stripping sidewalks and curb installation on Bartlett Street
• Complete Streets Project
o No work planned
• Sewer System Rehabilitation
o TV inspection of sewer and drain at various locations
• Sidewalk Repair
o No work planned; Watertown Square delta work on hold until contractor returns
• 2020 Water Main Replacement
o Begin connecting residences to by-pass
o Replace fire hydrant on Evans Street near Nash Street (requires shutdown)
o Water main connections at Nash St. and Jensen Road (requires shutdown)
o Install sewer manhole on Essex Street
• Line Painting
o Night work throughout Town
• National Grid
o Continue Irving Street gas main relay
o Continue gas main relays on Forest Street
o Continue gas relay on Riverside Ave. (note extended work limits to N. Beacon Street and
#50 Riverside Ave.)
o Continue work on Templeton Parkway at Mt. Auburn Street
o No work on Belmont Street at Duff Street planned
Note: All work is weather -dependent and subject to change.