HomeMy Public PortalAboutWeek of 0727 Work PlanAnticioated Work —Week of July 27. 2020 • Common Street o Adjust curb layout at Common Street/Orchard Street splitter islands o Begin installation of truck island curbing • Road Program o Loam and seed and complete transitions and driveways on Chandler Street, Burnham Street and Bridgham Ave. o Loam and seed and complete transitions and driveways on Piermont Street and Tappan Ave. o Begin stripping sidewalks and curb installation on Bartlett Street • Complete Streets Project o No work planned • Sewer System Rehabilitation o TV inspection of sewer and drain at various locations • Sidewalk Repair o No work planned; Watertown Square delta work on hold until contractor returns • 2020 Water Main Replacement o Begin connecting residences to by-pass o Replace fire hydrant on Evans Street near Nash Street (requires shutdown) o Water main connections at Nash St. and Jensen Road (requires shutdown) o Install sewer manhole on Essex Street • Line Painting o Night work throughout Town • National Grid o Continue Irving Street gas main relay o Continue gas main relays on Forest Street o Continue gas relay on Riverside Ave. (note extended work limits to N. Beacon Street and #50 Riverside Ave.) o Continue work on Templeton Parkway at Mt. Auburn Street o No work on Belmont Street at Duff Street planned Note: All work is weather -dependent and subject to change.