HomeMy Public PortalAboutWeek of 0817 Work PlanAnticipated Work —Week of August 17, 2020 • Common Street o Continue installation of truck island apron o Continue landscaping at Spring Street o Install lighting • Road Program o Continue curb and sidewalk installation on Bartlett Street o Continue curb and sidewalk installation on Avon Road o Top course paving on Piermont Street, Tappan Ave., Chandler Street, Burnham Street and Bridgham Ave. pending sub -contractor availability • Complete Streets Project o No work planned • Sewer System Rehabilitation o TV inspection of sewer and drain at various locations • 2020 Water Main Replacement o Continue installing water main on Pine Street o Mobilize on Oak Street —install catch basin protection, tree protection and begin laying down by-pass pipe • National Grid o Continue Irving Street gas main relay o Continue gas main relays on Forest Street o Continue gas relay on Riverside Ave. (note extended work limits to N. Beacon Street and #50 Riverside Ave.) o Continue work on Templeton Parkway at Mt. Auburn Street o No work on Belmont Street at Duff Street planned Note: All work is weather -dependent and subject to change.