HomeMy Public PortalAboutWeek of 0824 Work PlanAnticipated Work —Week of August 24, 2020
• Common Street
o Continue landscaping and drainage at Spring Street
o Install supplemental drainage on Marion Road
o Begin raising castings
o Punch list work project -wide
• Road Program
o Finish driveway and transitions on Bartlett Street
o Continue curb and sidewalk installation on Avon Road
o Drainage installation on Frank Street and Louise Street
• Complete Streets Project
o No work planned
• Sewer System Rehabilitation
o TV inspection of sewer and drain at various locations
• 2020 Water Main Replacement
o Continue installing water main on Nash Street
o Install sewer manhole on Nash Street
o Begin connecting houses on Oak Street to water supply by-pass, pending chlorination
results
• National Grid
o Continue Irving Street gas main relay
o Continue gas main relays on Forest Street
o Continue gas relay on Riverside Ave. (note extended work limits to N. Beacon Street and
#50 Riverside Ave.)
o Continue work on Templeton Parkway at Mt. Auburn Street
o No work on Belmont Street at Duff Street planned
Note: All work is weather -dependent and subject to change.