HomeMy Public PortalAboutWeek of 0831 Work PlanAnticipated Work —Week of August 31, 2020 • Common Street o Mill transition areas o Top course paving tentatively scheduled for September 4 • Road Program o Continue curb and sidewalk installation on Avon Road o Begin curb and sidewalk installation on Bellevue Road o Finish drainage/stormwater installations on Frank Street and Louise Street o Lower castings on Frank Street and Louise Street o Road reclamation on Downey Street, Kimball Road, Nichols Ave., Frank Street, and Louise Street • Complete Streets Project o Line painting • Sewer System Rehabilitation o Insituform is scheduled to install cast -in -place pipe on the following streets: Frank Street (drain) York Ave Riverside Street (between No Beacon St & Alfred Road) Belmont St (between Hardy Ave & Warwick Road) Orchard St (between Waverly Ave & Lexington St) Elmwood Ave (drain) Porter Street (drain) No Beacon St (between No Beacon Ct & Ladd St) Consult street notifications for service impacts o Replace sewer main on York Ave. at Hamden Ave. • 2020 Water Main Replacement o Continue installing water main on Nash Street and Essex Street o Begin water main installation on Oak Street, including connection points (requires water main shutdown) • National Grid Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed below: o Continue Irving Street gas main relay o Continue gas main relays on Forest Street o Continue gas relay on Riverside Ave. (note extended work limits to N. Beacon Street and #50 Riverside Ave.) o Continue work on Templeton Parkway at Mt. Auburn Street Note: All work is weather -dependent and subject to change.