HomeMy Public PortalAboutWeek of 1101 Work PlanAnticipated Work —Week of November 1. 2021
• 2020 Road Program & Common Street (Onyx Corporation)
o Punch list work (all work areas)
• 2021 Road Program (Lorusso Corporation)
o Punch list work (all work areas)
• WaverleV Ave. Road Reconstruction (Lorusso Corporation)
o Punch list work
• 2021 Sanitary Sewer Investigations (National Water Main)
o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the Protect 2,
Project 3 and 4 work areas. No interruption of water or sewer service is anticipated, however there may
be temporary road closures and/or parking restrictions
o Sanitary Sewer Rehabilitations Contract 21-01S (National Water Main)
o Contractor will begin cleaning and inspection of various sewer and drain mains within the project area
• Water Service Replacement Program (Paolini LLC)
o Continue water service replacements at #204 Acton Street, #8, #12, #16-18, #24-26, #45-47 Oakland
Street; #23-25, #27-29 Morton Street; and #17-19 Howard Street
o In the spring, the contractor will perform permanent repairs of all trenches
o Bromfield Street Water Main Replacement (Paolini LLC)
o Continue trench repairs and site cleanup
o In the spring, the contractor will perform permanent trench repairs
o Sidewalk Rehabilitation (Century Paving)
o Begin complete streets work at Casey Park and sidewalk repairs on Main Street at Pleasant Street and
Galen Street
o Line Painting (KS Corporation)
o NIGHT WORK —line painting, town -wide
• National Grid Gas Work
Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed
below:
o Continue gas main replacement on Cottage Street
o Continue gas main replacement on Lovell Road
o Continue gas main replacement on George Street and Wilson Ave.
o Continue replacement of sidewalk panels damaged during gas main installation