Loading...
HomeMy Public PortalAboutWhites Sidewalk May 26TOWN OF WATERTOWN DEPARTMENT OF PUBLIC WORKS (P) 617-972-6420 124 ORCHARD STREET (F) 617-972-6402 WATERTOWN MA 02472 Gregory M. St. Louis, PE Superintendent May 25, 2021 SIDEWALK, DRIVEWAY AND HANDICAPPED RAMP REPAIRS Whites Avenue ( Main Street to Summer Street ) The Watertown Department of Public Works and our contractor, Century Paving Inc, will begin the repair of concrete sidewalks, handicap ramps and driveway aprons. This work is part of our annual sidewalk maintenance and repair program, where selected sidewalk panels and driveway aprons that are heavily damaged and/or trip hazards are repaired or replaced. The work is scheduled to start, WEATHER PERMITTING, Wednesday, May 26, 2021 and will run for several days thereafter. Typical work hours will be 7 AM to 4 PM. • During the concrete installation process wooden planks will be placed across walkways to access your residence. • Please do not park your car next to any areas marked in front of your residence during construction. • You will be notified by the Contractor prior to any work that affects access to your driveway. Driveways may remain closed up to three days to permit the concrete to cure. • Please note that there may be lapses in time between sidewalk excavation, installing wood sidewalk forms, and final concrete work. • Adjustments necessary to make sidewalks and driveways ADA compliant may require minor regrading of areas beyond the back of sidewalk, such as landscaping, driveways or walkways. The Department will match existing materials and finishes to the maximum extent possible. • The Watertown Police will be informed of the construction and its effects, including the need for extended on -street parking due to driveway repairs. We apologize for the short notice and understand that the process is noisy, messy and disruptive and apologize in advance for any inconvenience you may experience. We know you will enjoy the improved appearance and condition of your sidewalks for many years in the future. Should you have any questions, please e-mail dpwdept(a�-watertown-ma.gov or you may call Ed Baptista, Highway Supervisor, at 617-972.6420. Sincerely, Gregory St Louis, PE, LEED, AP BD+C Superintendent of Public Works TOWN OF WATERTOWN DEPARTMENT OF PUBLIC WORKS (P) 617-972-6420 124 ORCHARD STREET (F) 617-972-6402 WATERTOWN MA 02472 Gregory M. St. Louis, PE Superintendent May 25, 2021 Dear Residents on Desmond Avenue, Lexington Street and Bancroft Street: The Department of Public Works and our contractor, Lorusso Corp, will start installing the final asphalt wearing surface on your street(s) in the order presented, WEATHER PERMITTING, on Wednesday, May 26, 2021 and finish on Thursday, May 27, 2021. The street will be closed to motor vehicle traffic during this paving process. Please park your motor vehicles out of the construction area on the intersecting side streets if necessary. Please do not park your car on your street or on your driveway to avoid being blocked in during the construction. Vehicles not removed from the street by 7:00 am, will be towed, per order of the Department of Public Works. The Watertown Police will be informed of the construction and its effects. We understand that the process is noisy, messy and disruptive and apologize in advance for inconvenience you may experience. We know you will enjoy the improved appearance and condition of your roadway for many years in the future. Should you have any questions, please call the office at 617-972-6420. All work will follow the Commonwealth of Massachusetts COVID-19 GUIDELINES AND PROCEDURES FOR ALL CONSTRUCTION SITES & WORKERS AT ALL PUBLIC WORKS PROJECTS Sincerely, egory St. Louis LEED AP BD+C Superintendent of Public Works Sheet Letters 2021 DesmondAve, Levingtoi7St and Bancroft St Final pave 5-26-21