Three Week Look Ahead 7-22-19 through 8-9-19
CREWS:
A. Commonwealth Construction & Utilities, Inc
Week Of
TASK
CREW
7/22/19
through
7/26/19
A. Crew: Now that the pipes are connected to the homes our crew will continue
working starting at Piermont to Tappan to Sparkill and then to Nyack. This work is
expected to last over the next two weeks.
A. CCU 4 Man Crew
7/29/19
through
8/2/19
A. Crew: As well as continuing the work above we will also do Installation of hydrants
and gate valves
A. CCU 4 Man Crew
8/5/19
through
8/9/19
A. Crew: Test and disinfecting the pipes for a final hook up to each homeowner to
follow
--
A. CCU 4 Man Crew