HomeMy Public PortalAboutPiermont_St_3-Week_Look_Ahead_8-5Commonwealth Construction & Utilities, Inc. Three Week Look Ahead 8-5-19 through 8-23-19 CREWS: A. Commonwealth Construction & Utilities, Inc Week Of TASK CREW 8/5/19 through 8/23/19 A. Crew: CCU will be completing the water main portion of the project on Monday August 5, 2019. Disinfecting and testing will be occurring the week of the 5`h Paving and services will be occurring the week of the 5`h and the following 2 weeks. A. CCU 4 Man Crew