HomeMy Public PortalAboutPiermont_St_3-Week_Look_Ahead_8-5Commonwealth Construction & Utilities, Inc.
Three Week Look Ahead 8-5-19 through 8-23-19
CREWS:
A. Commonwealth Construction & Utilities, Inc
Week Of
TASK
CREW
8/5/19
through
8/23/19
A. Crew: CCU will be completing the water main portion of the project on Monday
August 5, 2019. Disinfecting and testing will be occurring the week of the 5`h
Paving and services will be occurring the week of the 5`h and the following 2
weeks.
A. CCU 4 Man Crew