HomeMy Public PortalAboutWatertown Schedule 1Commonwealth Construction & Utilities, Inc. —
Three Week Look Ahead 6-24-19 through 7-12-19
A. CCU 4 Man Crew
B.
Week Of
TASK
CREW
6/24/19
through
6/28/19
A. Crew: Notification to residents on Tuesday 6/25/2019
hursday 6/27/2019 Tree Protection, Silt Sacks and layout
/28/19 Start installation of bypass
A. CCU 4 Man Crew
7/1/19
through
7/5/19
A. Crew: Continue Installing by-pass. No work will be performed on 7/4 and 7/5/2019
for holiday observance
A. CCU 4 Man Crew
7/8/1 g
through
7/12/19
A. Crew: Cut in hydrant at Sparkill St. Start work on Belmont St. Disinfecting and
sampling by pass and house hookups once bypass samples are complete
A. CCU 4 Man Crew
Hroonst will perform tree pruning prior to excavation of the main