HomeMy Public PortalAboutWatertown Schedule 1Commonwealth Construction & Utilities, Inc. — Three Week Look Ahead 6-24-19 through 7-12-19 A. CCU 4 Man Crew B. Week Of TASK CREW 6/24/19 through 6/28/19 A. Crew: Notification to residents on Tuesday 6/25/2019 hursday 6/27/2019 Tree Protection, Silt Sacks and layout /28/19 Start installation of bypass A. CCU 4 Man Crew 7/1/19 through 7/5/19 A. Crew: Continue Installing by-pass. No work will be performed on 7/4 and 7/5/2019 for holiday observance A. CCU 4 Man Crew 7/8/1 g through 7/12/19 A. Crew: Cut in hydrant at Sparkill St. Start work on Belmont St. Disinfecting and sampling by pass and house hookups once bypass samples are complete A. CCU 4 Man Crew Hroonst will perform tree pruning prior to excavation of the main