HomeMy Public PortalAbout2019 Road PresentationPublic Works Subcommittee Presentation
December 181 2018
.
.
.
Road Program Goals
Elements of Road Reconstruction
2018 Road Reconstruction Update
2019 Road Reconstruction List
Capital Projects and Planning
Complete Streets Policy Update
Summary
vown
Key Facts & Considerations
0 2018 Construction Season
2,700 feet of water main replacement
1,360 feet of sewer main replacement
125 feet of drain replacement
800 feet of gas main replacement (National Grid)
Work stoppage impacts
` 4,320 feet of road reconstruction
` 72 centerline miles of Town roads
55 miles of residential roads
Average width of residential roads is 25 feet
Town (2012 — 59)
million)
-Wide
Pavement Condition Index:
65
IV Total
Work
Backlog: $88 million(2012 -
$92
Road Reconstruction Progress
Program Activities
` Maintenance and Repair
Mill and overlay repairs
Is Full depth patch
Is Crack sealing
Sidewalk reconstruction
rrRoad Reconstruction
T ,
c, �Srlvw
v
II - Koaa reclamation Today's Discussion
L- Mill and overlay JI
Maintenance, Repair & Reconstruction
' Provide a variety of maintenance treatments to
prolong the useful life of less deteriorated
roadways
' Coordinate road reconstruction activities with
capital planning and utility work
' Seek long term planning and alternative funding for
large-scale projects
' Improve accessibility and safety for all users by
using "Complete Streets" principles
PROP.
SIDEWALK
4" LOAM
1:10 6" REVEAL
EXIST GROUND 1.5f', (T1P.} MAX.—2m-crv.)
B" GRAVEL BORROW. TYPE B
WHERE REQUIRED/DIRECTED BY
DPW SUPERINTENDENT (TYP.) -
EXIST. ROADWAY
PROP. ROADWAY
VARIES MATCH EXIST.
-- FULL DEPTH PAVEMENT RECLAMATION
GRAN. CURB - TYPE VA-4
4" LOAM & SEED
TYPICAL SEC71ON
FULL DEPTH PAVEMENT DEPTH PAVEMENT RECLAMATION
NOT TO SCALE
PROP.
SIDEWALK
t-0 5'-0" (MIN.)
(MIN.)
1:10
MAX. _1.5x' TYP
4" LOAM & SEED
EXIST. GROUND
4" CEM. CONC,
WAIN SURFACE
- 4" LOAM & SEED
GRAN, CURB - TYPE VA-4
*CONSTRUCTION TOLERANCE 10.5%
Wato�PIilftre
lio
4g fownr
Reclamation
Grading and Compaction
Binder Paving
Curb Installation
Sidewalk, Driveway and Accessible Ramps
r,INfllllllllllll ��
Sidewalk, Driveway and Accessible Ramps
Planning and Notifications
' Winter —Develop Plans and Specifications
is Review streets with tree warden
Review driveways with Zoning Enforcement Officer
Develop conceptual plans for geometric changes
Review green infrastructure opportunities
Review sewer and drain infrastructure if needed
Planning and Notifications
Late Winter —Notify residents of planned work
is Provide scope of work and notification procedure
41 Remind residents of future moratorium
is Encourage residents to request street trees
is Notify residents of driveway impacts
10 Construction Notifications
is Before work begins
41 At significant milestones during the project
Arden Road
Priest Road
Before After
Malden Street
s.
Before
After
Spring 2019—Transition repairs to be finalized in 2019
Everett Avenue (Palfrey Street to Bartlett Street)
Spring
0C J
fairs to be tinalizea in lU1y
Edgecliff Road
ail
Before
Spring 2019—Top course paving &I %A I I %.A .I%,%A tJ I I I b
EdgeclifF Road Green Infrastrurfl,rP
10
10
Two tree trenches installed
under sidewalk
Provide stormwater treatment
and infiltration prior to entering
drainage system
Protect the Charles River and
helps meet EPA permit
requirements
Westland Road
rill N
1P
Ph
fi
Before
After
Spring 2019—Top course paving & landscaping
Woodleigh Road
F
Before
After
Spring 2019—Top course paving & landscaping
Hosmer Safe Routes to School
After
r,-
Spring 2019—Top course paving & landscaping
Common Street
Shut down for winter
Curb and sidewalk work between Common Street and Columbia
Street completed
Next phase will be from Columbia Street through
roundabout
Orchard Street Extension &Katherine Road
a
z
X
COUMOn STREEPr —�
srF
Developing a "Universe of Projects"
2012 & 2016 Pavement Management Inventory
' Windshield surveys
Maintenance records
Capital projects (proposed and completed)
10 Resident input
Developing the List
0 Prepare detailed cost estimates of high priority
streets
' Develop a program that fits within funding
constraints
10 Prioritize streets in greatest state of disrepair
' Continue ongoing preventative maintenance
' Consider alternative funding sources
' Consider geographic equity
Utility Coordination & Capital Planning
It Water main replacement program
Hunt Street
Wheeler Lane
Phillips Street
' Sewer and drain repairs
Maplewood Street (School St. to Commonwealth Road)
Copeland Street
' National Grid work stoppage
Proposed Streets
Bellevue Road (Channing Road to Common
Street)
' Avon Road
Chandler Street
Burnham Street
Bridgham Avenue
' Nichols Avenue (Dexter Avenue to Boylston
Street)
' Bartlett Street (including Everett Ave.)
Bellevue Road (Channing Road to Common St.)
w �.
• Gas main replaced in 2015
• Trench repairs, alligator
cracking, cracking at joints
• Berm, concrete sidewalks
IF
Watertown
Publisarks
ft.earleewr
rnRsmwn.^
• Gas main replaced in 2015
• Water main replaced in 2016
• Berm; sidewalk gaps
• Multiple cross and mainline trenches
IF
Watertown x�m�-rya
Publisarks
ft.earleewr
rnrsmwn.^
= ` M
lrf` jI � 1
Y
Gas main replaced in 2015
Water main replaced in 2016
Various sidewalk and curb materials
Multiple cross & mainline trenches
IF
Watertown
Publisarks
ft.earleewr
rnRsmwn.^
i
• Gas main replaced in 2016
• Water main replaced in 2017
• Granite curb, various sidewalks in disrepair
• Multiple cross and mainline trenches
IF
Watertown
Publlsarks
ft.eall eetWr
rnRsmwn.^
Nichols Ave. (Dexter Ave. to Boylston Street)
Nichols Ave.
650 feet long— 24 feet wide
Bartlett Street (including Everett Ave.)
www.mountauburnstreet.com
www.watertownsquareimprovements.com
MassDOT design and funding for Galen
Street/Nonantum Road/Watertown Street intersection
'- Arsenal Street corridor developer mitigation
City of Cambridge Belmont Street "facelift" from
Brimmer Street to Mount Auburn Street (2019)
Community Path Extension (Irving to Taylor) DCDP
Update
10 Policy adopted by Town Council on May 9, 2017
Complete Streets Prioritization Plan completed
' Applied to be a Tier 3 community
Raised crosswalk on Whites Ave.
is Widen path through Saltonstall Park
is Raised crosswalk on Warren Street at Cuniff School
41 Crosswalk improvements on Watertown Street at
Theurer Park
10 Received $280,000 grant funding for 2019
construction
Challenges
10 Limited number of vendors bidding on work
Reflected in bid prices
Affects schedule
' Weather
Severe weather conditions can lead to higher
than expected levels of deterioration on
streets
' Planned and unplanned utility work
Reduces road PCI and increases maintenance or
reconstruction needs
' Funding collector roads and longer streets
2019 Road Reconstruction List
Bellevue Road (Channing Road to Common Street)
Avon Road
' Chandler Street
Burnham Street
• Bridgham Avenue
• Nichols Avenue (Dexter Avenue to Boylston Street)
10 Bartlett Street (including Everett Ave.)