HomeMy Public PortalAboutThree Week Look Ahead Complete StreetsONYX - Three Week Look Ahead 4-6-20 through 4-24-20 2020 Watertown Complete Streets Ex-20-0001 CREWS: A. Onyx 3 man crew Week Of TASK CREW 4/6120 through 4/10/20 A. Crew: Tree protection for all Three locations/Sawcut for curb installation on Theurer Park and at Stop and Shop A. Onyx 3 man crew 4/13/20 through 4/17/20 A. Crew: Start excavating and installation of Cb's on Theurer Park/ start installation of curb and sidewalks A. Onyx 3 man crew 4/20/20 through 4/24/20 A. Crew: Finish curb and sidewalks/ Mill and pour concrete Island/pave A. Onyx 3 man crew