HomeMy Public PortalAboutThree Week Look Ahead Complete StreetsONYX - Three Week Look Ahead 4-6-20 through 4-24-20
2020 Watertown Complete Streets Ex-20-0001
CREWS:
A. Onyx 3 man crew
Week Of
TASK
CREW
4/6120
through
4/10/20
A. Crew: Tree protection for all Three locations/Sawcut for curb installation on
Theurer Park and at Stop and Shop
A. Onyx 3 man crew
4/13/20
through
4/17/20
A. Crew: Start excavating and installation of Cb's on Theurer Park/ start installation
of curb and sidewalks
A. Onyx 3 man crew
4/20/20
through
4/24/20
A. Crew: Finish curb and sidewalks/ Mill and pour concrete Island/pave
A. Onyx 3 man crew