HomeMy Public PortalAboutThree Week Look Ahead Complete Streets_1ONYX - Three Week Look Ahead 5-18-20 through 6-5-20
2020 Watertown Complete Streets Ex-20-0001
CREWS:
A. Onyx 3 man crew
Week Of
TASK
CREW
5/18/20
through
5/22/20
A. Finish grading pathway/ Install RRFB Base/ Curb and Sidewalk on one side of
the raised crosswalk.
A. Onyx 3 man crew
5/25/20
through
5/29/20
A. Install curb, Sidewalk, and install the other RRGB Base and conduit to the
existing pole.
A. Onyx 3 man crew
6/1/20
through
6/5/20
A. Excavate raised intersection and install conduit across the street. Prep and pave
intersection and pathways
A. Onyx 3 man crew