Loading...
HomeMy Public PortalAboutThree Week Look Ahead Complete Streets_1ONYX - Three Week Look Ahead 5-18-20 through 6-5-20 2020 Watertown Complete Streets Ex-20-0001 CREWS: A. Onyx 3 man crew Week Of TASK CREW 5/18/20 through 5/22/20 A. Finish grading pathway/ Install RRFB Base/ Curb and Sidewalk on one side of the raised crosswalk. A. Onyx 3 man crew 5/25/20 through 5/29/20 A. Install curb, Sidewalk, and install the other RRGB Base and conduit to the existing pole. A. Onyx 3 man crew 6/1/20 through 6/5/20 A. Excavate raised intersection and install conduit across the street. Prep and pave intersection and pathways A. Onyx 3 man crew