HomeMy Public PortalAboutThree Week Look Ahead Complete Streets_2ONYX - Three Week Look Ahead 6-29-20 through 7-17-20 2020 Watertown Complete Streets Ex-20-0001 CREWS: A. Onyx 3 man crew B. Lazarro Week Of TASK CREW 6/29/20 through 7/3/20 A. Onyx 3 man crew 7/6/20 through 7/10/20 A. Punch list all three sites then go to Bartlett St. and work on Road Rehab contract work./ Install Island on Watertown St. A. Onyx 3 man crew B. Pave Mill Watertown St. and Whites Ave. ???? B. Lazarro 7/13/20 through 7/17/20 A. Onyx 3 man crew B. Pave Mill Watertown St. and Whites Ave. ???? B. Lazarro