HomeMy Public PortalAboutComplete Streets Three Week Look AheadONYX.- Three Week Look Ahead 6-8-20 through 6-26-20
2020 Watertown Complete Streets Ex-20-0001
CREWS:
A. Onyx 3 man crew
B. Lazarro
Week Of
TASK
CREW
618/20
through
6/12/20
A. Install curb, Sidewalk, and install and RRGB Base on Warren St. Then install CB
and pipe to existing manhole
A. Onyx 3 man crew
6/15/20
through
through
6/19/20
A. Install curb, Sidewalk, and install and RRGB Base on School side of Warren St.
Then install remaining CB and pipe to existing manhole.
A. Onyx 3 man crew
B. Mill Watertown St. and Whites Ave.
B. Lazarro
6/22/20
through
6/26/20
A. Punch list all three sites then go to Bartlett St. and work on Road Rehab contract
work.
A. Onyx 3 man crew
B. Pave Mill Watertown St. and Whites Ave.
B. Lazarro