HomeMy Public PortalAboutThree Week Look Ahead Complete StreetsONYX - Three Week Look Ahead 4-20-20 through 5-8-20
2020 Watertown Complete Streets Ex-20-0001
CREWS:
A. Onyx 3 man crew
Week Of
TASK
CREW
4/20/20
through
4/24/20
A. Start installing curb and sidewalk at Stop and Shop entrance. Pour sidewalks
and pave gutter line.
A. Onyx 3 man crew
4/27/20
through
511 /20
A. Start excavating out existing concrete path on Whites Ave./ Start curb and
Sidewalk on short side.
A. Onyx 3 man crew
5/4/20
through
5/8/20
A. Finish shortside pouring sidewalks/ Start curb and Sidewalk on Long Side.
A. Onyx 3 man crew