HomeMy Public PortalAboutThree Week Look Ahead Complete StreetsONYX - Three Week Look Ahead 4-20-20 through 5-8-20 2020 Watertown Complete Streets Ex-20-0001 CREWS: A. Onyx 3 man crew Week Of TASK CREW 4/20/20 through 4/24/20 A. Start installing curb and sidewalk at Stop and Shop entrance. Pour sidewalks and pave gutter line. A. Onyx 3 man crew 4/27/20 through 511 /20 A. Start excavating out existing concrete path on Whites Ave./ Start curb and Sidewalk on short side. A. Onyx 3 man crew 5/4/20 through 5/8/20 A. Finish shortside pouring sidewalks/ Start curb and Sidewalk on Long Side. A. Onyx 3 man crew