HomeMy Public PortalAboutThree Week Look Ahead Watertown Phase 1 and 2ONYX - Three Week Look Ahead 4-6-20 through 4-24-20
Watertown Rehab Phase 1 and 2
CREWS:
A. Onyx Crew
B. Lazaro Pulverizing and Grading
C. Lazaro Paving
D. Jemenez
Week Of
TASK
CREW
4/6/20
through
4/10/20
A. Crew: Tree protection, silt sacks
A. Onyx Crew
4/13/20
through
4/17/20
A. Crew: Work on Drainage on Chandler St., Burnham St., and Bridgham St.
B. Crew: lower castings on Chandleer St., Burnham St., and Bridgham St.,
Piermont St. and Tappen Ave.
A. Onyx Crew
D. Jemenez
4/20/20
through
4/24/20
A. Crew: Work on Drainage on Piermont St. and Tappen Ave.
A. Onyx Crew
B. Lazaro: Reclaim Chanler St., Burnham St., and Bridgham St.
B. Lazaro Pulverizing and Grading