HomeMy Public PortalAboutThree Week Look Ahead Watertown Phase 1 and 2_1ONYX - Three Week Look Ahead 4-20-20 through 5-8-20
Watertown Rehab Phase 1 and 2
CREWS:
A. Onyx Crew
B. Lazaro Pulverizing and Grading
C. Lazaro Paving
D. Jemenez
Week Of
TASK
CREW
4/20/20
through
4/24/20
A. Crew: Finish drainage on Piermont St. and Tappen Ave. Then install CB on
Downey Street.
A. Onyx Crew
4/27/20
through
5r1u20
A. Crew: Install CB's on Kimball Road
B. Lazaro: Reclaim and Grade Chanler St., Burnham St., and Bridgham St.
A. Onyx Crew
B. Lazaro Pulverizing and Grading
5/4/20
through
5/8/20
A. Crew:
Work on Drainage on Kimball Road
A. Onyx Crew
D. Crew: Start lowering castings on Bartlett St. then Bellevue Rd.
D. Jemenez
B. Lazaro: Reclaim and Grade Piermont St. and Tappen Ave.
B. Lazaro Pulverizing and Grading