Loading...
HomeMy Public PortalAboutThree Week Look Ahead Watertown Phase 1 and 2_2ONYX - Three Week Look Ahead 5-18-20 through 6-5-20 Watertown Rehab Phase 1 and 2 CREWS: A. Onyx Crew B. Lazaro Pulverizing and Grading C. Lazaro Paving D. Jemenez E. DaPonte F. F & C Concrete Week Of TASK CREW 5/18/20 through 5/22/20 A. Crew: Finish Tree Trenches on Piermont St. and Tappen Ave. Start installing curb and Chandler St. and Burnham St. E. DaPonte Start Curb and Sidewalk on Chandler St. A. Onyx Crew E. DaPonte 5/25/20 through 5/29/20 A. Crew: Prep Sidewalks for DaPonte on Chandler and Burnham/ Start excavating for Curb on Piermont and Tappen Ave. A. Onyx Crew F. F & C Concrete to start installing curb on Piermont and Tappen St. F. F & C Concrete E. DaPonte Continue Curb and Sidewalk on Chandler St. and Burnham E. DaPonte 6/1 /20 through 6/5/20 A. Crew: Start excavating and installing curb on opposite side of Chandler St. and Burnham St./ Continue excavation and preping for Curb and Sidewalk for Piermont and Tappen St. A. Onyx Crew F. F & C Concrete to continue installing curb and pour sidewalk on Piermont and Tappen St. F. F & C Concrete E. DaPonte Continue Curb and Sidewalk on Chandler St. and Burnham E. DaPonte