HomeMy Public PortalAboutThree Week Look Ahead Watertown Phase 1 and 2_3ONYX - Three Week Look Ahead 6-29-20 through 7-17-20
Watertown Rehab Phase 1 and 2
CREWS:
A. Onyx Crew
B. Lazaro Pulverizing and Grading
C. Lazaro Paving
D. Jemenez
E. DaPonte
F. F & C Concrete
Week Of
TASK
CREW
6/29/20
through
7/3/20
A. Crew: Start grading for sidewalk on Piermont and Tappen Ave.
A. Onyx Crew
E. Finish installing curb on Piermont and Tappen Ave.
E. DaPonte
7/6/20
through
7/10/20
A. Crew: Continue grading for sidewalk on Piermont and Tappen Ave.
A. Onyx Crew
E. Start forming and pouring sidewalks on Piermont and Tappen Ave.
E. DaPonte
E. DaPonte continue to form and pour Driveways on Chandler St.
E. DaPonte
Onyx (Peters crew)
7/13/20
through
7/17/2
A. Crew: Start excavating for curb on Bartlett St..
A. Onyx Crew
E. Continue forming and pouring sidewalks on Piermont and Tappen Ave.
E. DaPonte
E. Finish forming and pourjing sidewalks on Chandler St. then loam and seed
Piermont and Tappen Ave.
E. DaPonte
Onyx (Peters crew)