HomeMy Public PortalAboutThree Week Look Ahead Watertown RehabONYX - Three Week Look Ahead 3-23-20 through 4-10-20
Watertown Rehab Phase 1 and 2
CREWS:
A. Onyx Crew
B. Garitty Reclamation/Larusso
C. Brox
Week Of
TASK
CREW
3/23/20
through
3/27/20
A. Crew: Tree protection, silt sacks, and lowering of castings on Chandler St.
A. Onyx Crew
3/30/20
through
4/3/20
A. Crew: Work with Garitty Reclamation on the pulverization of the streets./lower
casting on Piermont St. and Tappen Ave.
B. Crew: Pulverize Chandler St.
A. Onyx Crew
B. Garitty Reclamation/Larusso
4/6/20
through
throug0
4/10/2
A. Crew: work with paving crew/ finish lower castings on Piermont St. and Tappen
Avenue.
A. Onyx Crew
B. Crew: Pulverize Piermont St. and Tappen Ave. C.
Brox: Pave Chandler St.
113. Garitty Reclamation/Larusso
IC. Brox