HomeMy Public PortalAboutThree Week Look Complete StreetsONYX - Three Week Look Ahead 3-23-20 through 4-10-20
2020 Watertown Complete Streets Ex-20-0001
CREWS:
A. Onyx 3 man crew
Week Of
TASK
CREW
3/23/20
through
3/27/20
A. Crew: Tree protection for all Three locations/Sawcut for curb installation on
Theurer Park
A. Onyx 3 man crew
3/30/20
through
4/3/20
A. Crew: Start excavating and installation of Cb's on Theurer Park/ start installation
of curb and sidewalks
A. Onyx 3 man crew
4/6/20
through
4/10/20
A. Crew: Finish curb and sidewalks/ Mill and pour concrete Island/pave
A. Onyx 3 man crew