Loading...
HomeMy Public PortalAboutThree Week Look Complete StreetsONYX - Three Week Look Ahead 3-23-20 through 4-10-20 2020 Watertown Complete Streets Ex-20-0001 CREWS: A. Onyx 3 man crew Week Of TASK CREW 3/23/20 through 3/27/20 A. Crew: Tree protection for all Three locations/Sawcut for curb installation on Theurer Park A. Onyx 3 man crew 3/30/20 through 4/3/20 A. Crew: Start excavating and installation of Cb's on Theurer Park/ start installation of curb and sidewalks A. Onyx 3 man crew 4/6/20 through 4/10/20 A. Crew: Finish curb and sidewalks/ Mill and pour concrete Island/pave A. Onyx 3 man crew