HomeMy Public PortalAboutWatertown Phase 1 and 2 Reclaim Paving ScheduleONYX - Three Week Look Ahead 11-16-20 through 12-4-20
Watertown Rehab Phase 1 and 2
CREWS:
A. Onyx Crew B. Onyx Crew C. Onyx Crew
C. Lazaro Paving
D. Jimenez
Week Of
TASK
CREW
11/16/20
through
11/20/20
A. Onyx Crew: Continue Curb and Sidewalk on Wheeler Ln..
A. Onyx Crew
B. Onyx Crew: Continue Curb and Sidewalk on Frank and Louise
B. Onyx Crew
D. Jimenez: Raise castings on Kimball and Bellevue and Downey St., Wheeler
lane, Nichols, Common St.(Mon, Tue, Fri, Mon of following week)
D. Jimenez
11/23/20
through
11 /27/20
A. Onyx Crew: Finish loam and driveways, then clean up Nichols
A. Onyx Crew
B Onyx Crew: Finish loam and driveways, pour sidewalk If anby on Frank and
Louise/Bellevue (behind guardrail)
B. Onyx Crew
11/30/20
through
12/4/20
TBD/Weather permitting
A. Onyx Crew
B. Onyx Crew
Note: Guard Rail: Dipping Thursday, picked up Friday and Installed on Monday
Paving: Hand crew to pave Whites Ave, Columbia St. and the puddle on the path. Monday pave Frank/Louise, and Downey
Tuesday pave Bellevue and Kimball
Irrigation: Friday to fix heads various locations
11-24-20 Eversourse and Dagle on Common St.