Loading...
HomeMy Public PortalAboutWatertown Phase 1 and 2 Three Week Look Ahead_1ONYX - Three Week Look Ahead 4-19-21 through 5-7-21 Watertown Rehab Phase 1 and 2 CREWS: A. Onyx Crew B. FC Concrete and Granite Installers C. Lazaro Paving D. Jimenez Week Of TASK CREW 4/19/21 through 4/23/21 A. Onyx Crew: Mobilize Site and start removing curb and sidewalk on Nichols St. A. Onyx Crew B. FC to start installing curb and sidewalk on Nichols St. B. FC Concrete and Granite Installers 4/26/21 through 4/30/21 A. Onyx Crew: Continue to istall curb and sidewalk on Nichols A. Onyx Crew B. Onyx Crew: Finish the flashing beacon on North Beacon St. B. Onyx Crew B. FC to Continuet installing curb and sidewalk on Nichols St. B. FC Concrete and Granite Installers 5/3/21 through 5/7/21 A. Onyx Crew: Continue to istall curb and sidewalk on Nichols A. Onyx Crew B. FC to Continuet installing curb and sidewalk on Nichols St. B. FC Concrete and Granite Installers