HomeMy Public PortalAboutWatertown Phase 1 and 2 Three Week Look Ahead_2ONYX - Three Week Look Ahead 5-24-21 through 6-28-21
Watertown Rehab Phase 1 and 2
CREWS:
A. Onyx Crew
B. FC Concrete and Granite Installers
C. Lazaro Paving
D. Jimenez
Week Of
TASK
CREW
5/24/21
through
5/28/21
A. Onyx Crew: Continue to istall curb and sidewalk on Nichols
A. Onyx Crew
B. FC to Continue installing curb and sidewalk on Nichols St.
B. FC Concrete and Granite Installers
5/31/21
through
6/4/21
A. Onyx Crew: Finish installing curb and sidewalk on Nichols/ Start installing
additional curb and sidewalk on Dexter St.
A. Onyx Crew
B. FC to Continue installing curb and sidewalk on Nichols St.
a. Onyx Crew
6/7/21
through
6/11 /21
A. Onyx Crew: Start raised table work on Nichols @ Dexter St.
A. Onyx Crew
D. Jimenez: Start raising structures on Nichols St.
D. Jimenez
Note: Hydroseed Tuesday 6/1 various streets
Line striping need a plan from Worldtech to set up a date.