HomeMy Public PortalAboutWatertown Phase 1 and 2 Three Week Look Ahead_2ONYX - Three Week Look Ahead 5-24-21 through 6-28-21 Watertown Rehab Phase 1 and 2 CREWS: A. Onyx Crew B. FC Concrete and Granite Installers C. Lazaro Paving D. Jimenez Week Of TASK CREW 5/24/21 through 5/28/21 A. Onyx Crew: Continue to istall curb and sidewalk on Nichols A. Onyx Crew B. FC to Continue installing curb and sidewalk on Nichols St. B. FC Concrete and Granite Installers 5/31/21 through 6/4/21 A. Onyx Crew: Finish installing curb and sidewalk on Nichols/ Start installing additional curb and sidewalk on Dexter St. A. Onyx Crew B. FC to Continue installing curb and sidewalk on Nichols St. a. Onyx Crew 6/7/21 through 6/11 /21 A. Onyx Crew: Start raised table work on Nichols @ Dexter St. A. Onyx Crew D. Jimenez: Start raising structures on Nichols St. D. Jimenez Note: Hydroseed Tuesday 6/1 various streets Line striping need a plan from Worldtech to set up a date.