HomeMy Public PortalAboutWatertown Phase 1 and 2 Three Week Look Ahead_3ONYX - Three Week Look Ahead 5-31-21 through 6-25-21
Watertown Rehab Phase 1 and 2
CREWS:
A. Onyx Crew
B. FC Concrete and Granite Installers
C. Lazaro Paving
D. Jimenez
Week Of
TASK
CREW
6/7/21
through
6/11 /21
A. Onyx Crew: Finish installing curb and sidewalk on Nichols/ finish installing
additional curb and sidewalk on Dexter St.
A. Onyx Crew
A. Onyx Crew: Start raised table work on Nichols @ Dexter St.
A. Onyx Crew
B. FC to Continue installing curb and sidewalk on Nichols St.
B. FC Concrete and Granite Installers
6/14/21
through
6/18/21
A. Onyx Crew: Finish raised table work on Nichols @ Dexter St.
A. Onyx Crew
D. Jimenez: Start raising structures on Nichols St./Wheeler 6/14 and 6/15
D. Jimenez
C. Lazaro Paving to start milling and finish paving Wheeler and Nichols Ave.
C. Lazaro Paving
6/21/21
through
6/25/21
A. Onyx Crew: Start Punchlist Items
A. Onyx Crew
C. Lazaro Paving to start milling and finish paving Wheeler and Nichols Ave.
C. Lazaro Paving
Note: