Loading...
HomeMy Public PortalAboutWatertown Phase 1 and 2 Three Week Look Ahead_3ONYX - Three Week Look Ahead 5-31-21 through 6-25-21 Watertown Rehab Phase 1 and 2 CREWS: A. Onyx Crew B. FC Concrete and Granite Installers C. Lazaro Paving D. Jimenez Week Of TASK CREW 6/7/21 through 6/11 /21 A. Onyx Crew: Finish installing curb and sidewalk on Nichols/ finish installing additional curb and sidewalk on Dexter St. A. Onyx Crew A. Onyx Crew: Start raised table work on Nichols @ Dexter St. A. Onyx Crew B. FC to Continue installing curb and sidewalk on Nichols St. B. FC Concrete and Granite Installers 6/14/21 through 6/18/21 A. Onyx Crew: Finish raised table work on Nichols @ Dexter St. A. Onyx Crew D. Jimenez: Start raising structures on Nichols St./Wheeler 6/14 and 6/15 D. Jimenez C. Lazaro Paving to start milling and finish paving Wheeler and Nichols Ave. C. Lazaro Paving 6/21/21 through 6/25/21 A. Onyx Crew: Start Punchlist Items A. Onyx Crew C. Lazaro Paving to start milling and finish paving Wheeler and Nichols Ave. C. Lazaro Paving Note: