HomeMy Public PortalAboutWatertown Phase 1 and 2 Three Week Look aheadONYX - Three Week Look Ahead 10-9-20 through 10-23-20
Watertown Rehab Phase 1 and 2
CREWS:
A. Onyx Crew B. Onyx Crew C. Onyx Crew
B. Lazaro Pulverizing and Grading
C. Lazaro Paving
D. Jimenez
E. DaPonte
F. F & C Concrete
Week Of
TASK
CREW
10/19/20
through
10/23/20
A.
Onyx Crew: Continue Curb and Sidewalk on Downey St.
A. Onyx Crew
B. Onyx Crew: Continue Curb and Sidewalk on Frank and Louise
B. Onyx Crew
D. Jimenez: Raise castings on Kimball and Bellevue and Downey St.
D. Jimenez
10/26/20
through
10/30/20
A.
Onyx Crew:
Finish loam and Sidewalk on Downey St.
A. Onyx Crew
B. Onyx Crew: Continue Curb and Sidewalk on Frank and Louise
B. Onyx Crew
11 /2/20
through
11/6/20
A. Onyx Crew:
ready for binder.
Remove asphalt on Wheeler Ln./ Add gravel fine grade and get
A. Onyx Crew
B. Onyx Crew: Finish loam and Sidewalk on Frank and Louise
B. Onyx Crew