HomeMy Public PortalAboutWatertown Phase I and II three week look aheadONYX - Three Week Look Ahead 5-10-21 through 5-28-21
Watertown Rehab Phase 1 and 2
CREWS:
A. Onyx Crew
B. FC Concrete and Granite Installers
C. Lazaro Paving
D. Jimenez
Week Of
TASK
CREW
5/10/21
through
5/14/21
A. Onyx Crew: Continue to istall curb and sidewalk on Nichols
A. Onyx Crew
A. Onyx Crew: Finish the flashing beacon on North Beacon St.
A. Onyx Crew
B. FC to Continuet installing curb and sidewalk on Nichols St.
B. FC Concrete and Granite Installers
5/17/21
through
5/21 /21
A. Onyx Crew: Continue to istall curb and sidewalk on Nichols
A. Onyx Crew
B. FC to Continuet installing curb and sidewalk on Nichols St.
a. Onyx Crew
5/24/21
through
hroug1
A. Onyx Crew: Continue to istall curb and sidewalk on Nichols
A. Onyx Crew
B. FC to Continuet installing curb and sidewalk on Nichols St.
B. FC Concrete and Granite Installers
Note: Hydroseeding various streets Thursday 5/13
Signs no parking Friday 5/14