HomeMy Public PortalAboutWatertown Three Week Look AheadONYX - Three Week Look Ahead 10-9-20 through 10-23-20
Watertown Rehab Phase 1 and 2
CREWS:
A. Onyx Crew B. Onyx Crew C. Onyx Crew
B. Lazaro Pulverizing and Grading
C. Lazaro Paving
D. Jimenez
E. DaPonte
F. F & C Concrete
Week Of
TASK
CREW
10/5/20
through
10/9/20
A.
Onyx Crew:
Continue to install curb and sidewalk on Bellevue St.
A. Onyx Crew
B. Onyx Crew: Continue to install curb and sidewalk Kimball St.
B. Onyx Crew
10/12/20
through
10/16/20
A. Onyx Crew: Start Curb and Sidewalk on Nichols St.
A. Onyx Crew
B. Onyx Crew: Start Curb and Sidewalk on Frank and Louise
B. Onyx Crew
D. Jimenez: Raise castings on Kimball and Bellevue
D. Jimenez
10/19/20
throu
through
A.
Onyx Crew:
Continue Curb and Sidewalk on Downey St.
A. Onyx Crew
B. Onyx Crew: Continue Curb and Sidewalk on Frank and Louise
B. Onyx Crew