HomeMy Public PortalAbout100_023_North Beach Dune Maintenance - CosttoConstructEstimate_Tybee_15Oct14 MEMORANDUM `== :j22 ptir-
TO: Diane Schleicher, City Manager—City of Tybee Island'E `'
FROM: Erik J. Olsen, P.E., Ga. 011051 V OISefl
associates, inc.
Coastal Engineering
DATE: 15 October 2014
RE: North Beach Dune Maintenance Project (2014/15)
Opinion of Probable Cost-to-Construct
Pursuant to your most recent inquiry, I would estimate the cost to "replicate" the 2002
North Beach dune enhancement project as follows:
Permit Renewal $2,100
Survey of Shorefront (ARC) $5,200
Engineering Plan/Bid Docs $25,000
Bid/Sand Source Evaluation $5,000
Contract for Sand Placement $450,000 budget
Contract Admin (Engineer) $7,500
Daily Contract Supervision by TBD
Tybee Island Personnel
Estimate $494,800
Say $500K plus staff time
The actual cost to construct would be subject to a bid or proposal solicitation. If budget
limited, the sand placement volume could be adjusted to meet any such constraints.
Thank you for your consideration in this matter.
olsen associates, inc. 1 2618 Herschel Street I Jacksonville, FL 32204 1 904.387.6114 I FAX 904.384.7368