Loading...
HomeMy Public PortalAboutThree Week Look Ahead Common St. Watertown 7-30-18ONYX - Three Week Look Ahead 8/17/20 through 9/4/20 CREWS: A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew D. Lazarro F. Jimenez Week Of TASK CREW 8/17/20 through 8/21 /20 A. Crew: Finish work at the retention area and (install lights if I ever get Dagle), then pour panels that need to be poured. A. Onyx 4 Man Crew 8/24/20 through 8/28/20 A. Crew: work on punch list and Lights A. Onyx 4 Man Crew F. Jimenez to raise castings F. Jimenez 9/1/20 through 9/4/20 A. Crew: Finish Pave Common St. (Brox Ind.)/ Punch list (Lights) A. Onyx 4 Man Crew