HomeMy Public PortalAboutThree Week Look Ahead Common St. Watertown 7-30-18ONYX - Three Week Look Ahead 8/17/20 through 9/4/20
CREWS:
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
D. Lazarro
F. Jimenez
Week Of
TASK
CREW
8/17/20
through
8/21 /20
A. Crew: Finish work at the retention area and (install lights if I ever get Dagle), then
pour panels that need to be poured.
A. Onyx 4 Man Crew
8/24/20
through
8/28/20
A. Crew: work on punch list and Lights
A. Onyx 4 Man Crew
F. Jimenez to raise castings
F. Jimenez
9/1/20 through
9/4/20
A. Crew: Finish Pave Common St. (Brox Ind.)/ Punch list (Lights)
A. Onyx 4 Man Crew