Loading...
HomeMy Public PortalAboutThree Week Look Ahead Complete StreetsONYX - Three Week Look Ahead 6-15-20 through 7-3-20 2020 Watertown Complete Streets Ex-20-0001 CREWS: A. Onyx 3 man crew B. Lazarro Week Of TASK CREW 6/15/20 through 6/19/20 A. Install curb, Sidewalk, and install and RRGB Base on School side of Warren St. Then install remaining CB and pipe to existing manhole. A. Onyx 3 man crew 6/22/20 through 6/26/20 A. Work on Chandler St. behind Jon Kings crew when they leave to go to Piermont St. A. Onyx 3 man crew B. Mill Watertown St. and Whites Ave. B. Lazarro 6/29/20 through 7/3/20 A. Punch list all three sites then go to Bartlett St. and work on Road Rehab contract work./ Install Island on Watertown St. A. Onyx 3 man crew B. Pave Mill Watertown St. and Whites Ave. B. Lazarro