2020 Watertown Complete Streets Ex-20-0001
CREWS:
A. Onyx 3 man crew
B. Lazarro
Week Of
TASK
CREW
6/15/20
through
6/19/20
A. Install curb, Sidewalk, and install and RRGB Base on School side of Warren St.
Then install remaining CB and pipe to existing manhole.
A. Onyx 3 man crew
6/22/20
through
6/26/20
A. Work on Chandler St. behind Jon Kings crew when they leave to go to Piermont
St.
A. Onyx 3 man crew
B. Mill Watertown St. and Whites Ave.
B. Lazarro
6/29/20
through
7/3/20
A. Punch list all three sites then go to Bartlett St. and work on Road Rehab contract
work./ Install Island on Watertown St.
A. Onyx 3 man crew
B. Pave Mill Watertown St. and Whites Ave.
B. Lazarro