HomeMy Public PortalAboutThree Week Look Ahead Watertown Phase 1 and 2ONYX - Three Week Look Ahead 6-15-20 through 7-3-20 Watertown Rehab Phase 1 and 2 CREWS: A. Onyx Crew B. Lazaro Pulverizing and Grading C. Lazaro Paving D. Jemenez E. DaPonte F. F & C Concrete Week Of TASK CREW 6/15/20 through 6/19/20 A. Crew: Continue to prep Sidewalks for DaPonte on Chandler and Burnham A. Onyx Crew E. DaPonte continue to form and our sidewalks on Chandler St. pour DaPonte 6/22/20 through 6/26/20 A. Crew: Start excavating for curb on Piermont and Tappen Ave. A. Onyx Crew E. Start installing curb on Piermont and Tappen Ave. E. DaPonte E. DaPonte continue to form and pour sidewalks on Chandler St. E. DaPonte 6/29/20 through 7/3/20 A. Crew: Continue excavating for curb on Piermont and Tappen Ave. A. Onyx Crew E. Continue installing curb on Piermont and Tappen Ave. E. DaPonte E. DaPonte continue to form and pour sidewalks on Chandler St. E. DaPonte