HomeMy Public PortalAboutThree Week Look Ahead Watertown Phase 1 and 2_1ONYX - Three Week Look Ahead 7-20-20 through 8-7-20 Watertown Rehab Phase 1 and 2 CREWS: A. Onyx Crew B. Lazaro Pulverizing and Grading C. Lazaro Paving D. Jemenez E. DaPonte F. F & C Concrete Week Of TASK CREW 7/20/20 through 7/24/20 A. Crew: Finish preping for sidewalk on Piermont and Tappen Ave. Loam and seed clean up site and get ready to move to Bartlet St. A. Onyx Crew E. Finish ourin sidewalks on Piermont and Ta en Ave. pouring pp E. DaPonte 7/27/20 through 7/31 /20 A. Crew: Start excavating for curb on Bartlett St.. A. Onyx Crew E. Finish forming and pouring sidewalks on Chandler St. Then off to Avon St. for curb and sidewalk work. E. DaPonte Onyx (Peters crew) 8/3/20 through 8/7/20 A. Crew: Continueing excavating for curb on Bartlett St.. A. Onyx Crew E. Start installing curb on Bartlett St. and Avon St. E. DaPonte Continue excavating for curb on Avon St. Onyx (Peters crew)