HomeMy Public PortalAboutThree Week Look Ahead Watertown Phase 1 and 2_2ONYX - Three Week Look Ahead 7-27-20 through 8-14-20
Watertown Rehab Phase 1 and 2
CREWS:
A. Onyx Crew
B. Lazaro Pulverizing and Grading
C. Lazaro Paving
D. Jemenez
E. DaPonte
F. F & C Concrete
Week Of
TASK
CREW
7/27/20
through
through
7/31/20
A. Crew: Start excavating for curb on Bartlett St..
A. Onyx Crew
F. Finish forming and pouring sidewalks on Chandler St. Then off to Avon St. for
curb and sidewalk work.
E. DaPonte
Onyx (Peters crew)
8/3/20
through
8/7/20
A. Crew: Continueing excavating for curb on Bartlett St..
A. Onyx Crew
F. Continue installing curb on Bartlett and Everett Ave.Then Start Sidewalks
F. F & C Concrete
E. Start installing curb on Avon St.
E. DaPonte
Onyx (Peters crew)
8/10/20
through
8/14/20
A./F Crew: Continueing prepimg sidewalks on Bartlett St. Continue pouring
sidewalks
A. Onyx Crew
F. F & C Concrete
E. Continue installing curb on Avon St.
E. DaPonte
ntinue excavating for curb on Avon St.
F
Onyx (Peters crew)