Loading...
HomeMy Public PortalAboutThree Week Look Ahead Watertown Phase 1 and 2_3ONYX - Three Week Look Ahead 8-17-20 through 9-4-20 Watertown Rehab Phase 1 and 2 CREWS: A. Onyx Crew B. Lazaro Pulverizing and Grading C. Lazaro Paving D. Jimenez E. DaPonte F. F & C Concrete Week Of TASK CREW 8/17/20 through 8/21/20 A. Crew: Finish Curb and Sidewalk on Bartlett St. and Everett Ave./ Peters crew to continue curb and sidewalk on Avon St. A. Onyx Crew Onyx (Peters crew) C. Lazaro Paving to pave Chandler, Burnham, Bridgham, Piermont st., and Tappan Ave. C. Lazaro Paving 8/24/20 through 8/28/20 A. Crew: Install new CB's and Tree pits on Frank and Louise St. A. Onyx Crew F. Continue installing curb and Sidewalk on Avon St. F. F & C Concrete Onyx (Peters crew) Onyx (Peters crew) to finish loam back of sidewalks and driveways then mobilize to Bellevue Rd. E. DaPonte Onyx (Peters crew) 9/1/20 9roug through A. Crew: Mobilize to Bellevue St. and start Curb and Sidewalk Work A. Onyx Crew F. F & C Concrete D. Jimenez to raise castings on Avon St. and Bartlet St./ Everett Ave. D. Jimenez Onyx (Peters Crew) to Start Curb and sidewalk on Bellevue St. Onyx (Peters crew)