HomeMy Public PortalAboutWeek of 0706 Work PlanAnticipated Work —Week of July 6, 2020
• Common Street
o Continue drainage, curb, and sidewalk installation at the Spring Street/Common Street
intersection
o Top course paving of Orchard Street Extension, Katherine Road, and Columbia Street
date to be determined
• Road Program
o Continue driveway forming and pouring on Chandler Street, Burnham Street and
Bridgham Ave.
o Form and pour sidewalks, accessible ramps, and driveways on Piermont Street and
Tappan Ave.
o As work pace permits, begin curb installation on Bartlett Street
• Complete Streets Project
o Install rumble strip on Watertown Street at Theurer Park
o Paving of Watertown Street, Whites Ave. and Linear Park date to be determined
• Sewer System Rehabilitation
o No work planned
• Sidewalk Repair
o Complete sidewalk repairs on Westminster Ave. and Bemis Street at Watertown Middle
School
o Begin sidewalk repairs on Spring Street between Summer Street and Palfrey Street
• 2020 Water Main Replacement
o Begin laying by-pass piping on Nash Street, Essex Street, and Pine Street
• National Grid
o Continue Irving Street gas main relay
o Continue gas main relays on Forest Street and Grandview Ave
o Continue work on Belmont Street at Duff Street
o Begin gas relay on Wheeler Lane at Riverside Ave.
o Note: service connections on all main relays on hold due to COVID-19