HomeMy Public PortalAboutWeek of 0103 Work PlanAnticipated Work —Week of January 3. 2022 • 2020 Sanitary Sewer Investigations (Umbro Construction) o Inland Waters will rehabilitate manholes within the work area • Sanitary Sewer Rehabilitations Contract 21-01S (National Water Main) o No work scheduled • 2021 Sanitary Sewer Investigations (National Water Main) o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the Project 2, Project 3 and 4 work areas. No interruption of water or sewer service is anticipated, however there may be temporary road closures and/or parking restrictions • National Grid Gas Work Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed below: o Continue gas main replacement on Lovell Road o Continue gas main replacement on Winter Street o Continue gas main replacement on Pine Street and Nash Street Note: All work is weather -dependent and subject to change.