HomeMy Public PortalAboutWeek of 0103 Work PlanAnticipated Work —Week of January 3. 2022
• 2020 Sanitary Sewer Investigations (Umbro Construction)
o Inland Waters will rehabilitate manholes within the work area
• Sanitary Sewer Rehabilitations Contract 21-01S (National Water Main)
o No work scheduled
• 2021 Sanitary Sewer Investigations (National Water Main)
o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the Project 2,
Project 3 and 4 work areas. No interruption of water or sewer service is anticipated, however there may
be temporary road closures and/or parking restrictions
• National Grid Gas Work
Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed
below:
o Continue gas main replacement on Lovell Road
o Continue gas main replacement on Winter Street
o Continue gas main replacement on Pine Street and Nash Street
Note: All work is weather -dependent and subject to change.