HomeMy Public PortalAboutWeek of 0214 Work PlanAnticipated Work —Week of February 14, 2022
• Sanitary Sewer Rehabilitations Contract 21-01S (National Water Main)
National Water Main will begin CIPP installation on the following streets:
Desmond Ave (between Grandview Avenue and Warren Street)
Carey Ave (between Lexington Street and King Street)
King Street (between Warren Street and Grandview Avenue)
Gilbert Street (between Highland Ave and Charles Street)
Partridge St (between Andrew Street and Highland Avenue)
Andrew St (between Partridge Street and Gleason Street)
Chapman St (between Highland Avenue and Main Street)
Chapman Street (between Carey Avenue and Madison Avenue)
See website for additional details
Note: If your home or business is connected to the sewer line being rehabilitated, your sewer service will be
temporarily blocked off from the sewer mainline once the liner is inflated.
During this time your water service is not shut off and you can continue using it for drinking, cooking and
other purposes, but residents are asked to limit water use. You should avoid taking showers or baths,
running your dishwasher and washing machine, and also be sure to turn off all sump pumps connected to
your sewer service. Flush your toilets sparingly. Using small amounts of water to wash your hands or brush
your teeth is okay. See web -site for additional information.
2021 Sanitary Sewer Investigations (National Water Main)
• Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the Protect 2,
Project 3 and 4 work areas as well as Chester Street, Boylston Street, Locke Street, Chapman Street,
Highland Ave., Morse Street, Fifth Ave., Westminster Ave., Linden Street, Waverley Ave. and Moxley
Field. No interruption of water or sewer service is anticipated, however there may be temporary road
closures and/or parking restrictions
• National Grid Gas Work
Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed
below:
o Continue gas main replacement on Winter Street
o Continue gas main replacement on Pine Street and Nash Street
o Continue gas main replacement on Fifth Avenue
• Eversource Electric
o Tree Tech will continue tree pruning around power lines, citywide