Loading...
HomeMy Public PortalAboutWeek of 0412 Work PlanAnticipated Work —Week of April 12, 2021 • 2020 Road Program & Common Street (Onyx Corporation) o Contractor plans to remobilize week of April 19 to complete punch list items, curb and sidewalk on Nichols Ave., and final paving of Wheeler Lane • 20-01W Water Main Replacement (Commonwealth Construction) o Final trench paving and sidewalk repairs (Essex St., Nash St., Pine St., and Oak St.) scheduled for later in April • 2021 Road Program (Lorusso Corporation) o Contractor will begin installing drainage and stormwater tree trenches on Gertrude Street, Goldie Street, and Elmwood Ave. • Sanitary Sewer Rehabilitations Contract 19-01S (Commonwealth Construction) o Inland Waters will be cleaning and inspecting various sewers and drains on various streets throughout Town, including N. Beacon Street, Riverside Street, and Galen Street. No interruption of water or sewer service is anticipated, however there may be temporary road closures and/or parking restrictions. • Sanitary Sewer Rehabilitations Contract 20-01S (Umbra & Sons Construction) Inland Waters will clean and TV inspect sewers on the following streets: o Brigham Street (Bailey Road to Garfield Street) o Chandler Street o Irving Street (Fifield Street to Riverside Street) o Perry Street o Standish Road (Locke Street to Bellevue Road) o Walnut Street (Lincoln Street to Center Street) Umbro & Sons Construction will continue sewer and drain repairs on Robbins Road Extension and install temporary pavement on Sheldon Road. • 2021 Sanitary Sewer Investigations (National Water Main) o Contractor will be cleaning and inspecting various sewer lines within the protect area. No interruption of water or sewer service is anticipated, however there may be temporary road closures and/or parking restrictions. • Highland Ave. Water Main Replacement —Lexington Street to Olney Street (Commonwealth Construction) o Contractor will continue to lay water main on Lexington Street • Pavement Preservation —Permanent Patch (Lorusso Corporation) o Contractor will continue permanent patch at various locations • National Grid Gas Work Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed below: o Continue gas main replacement on Green Street o Continue and complete gas main replacement on N. Beacon Street at Alfred Road o Continue gas main replacement on Francis Street o Continue gas main replacement on Bradshaw Street, between Loomis Street and #50 Loomis Street o Contractor (Midway) will begin restoration of Belmont Street at Duff Street —curb and sidewalk installation Note: All work is weather -dependent and subject to change.