HomeMy Public PortalAboutWeek of 0510 Work PlanAnticipated Work —Week of Mav 10. 2021
• 2020 Road Program & Common Street (Onyx Corporation)
o Continue curb and sidewalk on Nichols Ave.
o Loam and seed (project wide)
o As resources permit, begin crosswalk work at N. Beacon Street and Paul Street
• 20-01W Water Main Replacement (Commonwealth Construction)
o Continue final trench paving and repair of sidewalk panels damaged during water main
installation (Essex St., Nash St., Pine St., and Oak St.)
• 2021 Road Program (Lorusso Corporation)
o Contractor will complete installing drainage and stormwater tree trenches on Hazel Street
o Fine grade and binder pave Gertrude Street, Goldie Street, Elmwood Ave., and Grandview Ave.
o Begin curb and sidewalk installation on Gertrude Street, Goldie Street, Elmwood Ave., and
Grandview Ave.
• Sanitary Sewer Rehabilitations Contract 19-01S (Commonwealth Construction)
o Contractor will begin permanent patch and repair of sidewalk panels damaged during sewer
repair work at various locations
• Sanitary Sewer Rehabilitations Contract 20-01S (Umbra & Sons Construction)
Inland Waters will grout service connections in lined sewers on the following streets:
• Inland Waters will grout service connections in lined sewers on the following streets:
o Bailey Road
o Bridgham Avenue
o Garfield Street
o Gill Road
o Irving Street (Riverside Street to South Irving Park)
o Ladd Street
o Mt. Auburn Street (Amherst Road to Bailey Road; Bates Road to Franklin Street)
o Riverside Street (Perkins School to Irving Street)
o Russell Avenue (Bellevue Road to Brigham Street)
o Spruce Street (Lincoln Street to Mt. Auburn Street)
o Stoneleigh Circle
o Stoneleigh Road (Stoneleigh Circle to Bailey Road)
o Washburn Street (Franklin Street to Otis Street)
• 2021 Sanitary Sewer Investigations (National Water Main)
o Contractor will be cleaning and inspecting various sewer lines and begin flow isolation of sewers
(12:00 AM — 6:00 AM) within the project area. No interruption of water or sewer service is
anticipated, however there may be temporary road closures and/or parking restrictions.
• Sidewalk Repair Program (Century Paving)
o Contractor will continue complete streets curb and sidewalk work on Watertown Street at
Morse Street and California Street at Fifth Ave.
• National Grid Gas Work
Utility companies are responsible for notifying residents prior to conducting work, but planned work
is listed below:
o Continue gas main replacement on Green Street
o Continue gas main replacement on Oak Street
o Continue gas main replacement on Beechwood Ave.
o Continue gas main replacement on Cottage Street
Note: All work is weather -dependent and subject to change.