HomeMy Public PortalAboutWeek of 0517 Work PlanAnticipated Work —Week of May 17, 2021
• 2020 Road Program & Common Street (Onyx Corporation)
o Continue curb and sidewalk on Nichols Ave.
o Loam and seed (project wide)
o Continue crosswalk work at N. Beacon Street and Paul Street
• 20-01W Water Main Replacement (Commonwealth Construction)
o Continue repair of sidewalk panels damaged during water main installation (Essex St., Nash St.,
Pine St., and Oak St.)
• 2021 Road Program (Lorusso Corporation)
o Continue curb and sidewalk installation on Gertrude Street, Goldie Street, Elmwood Ave., and
Grandview Ave.
• Sanitary Sewer Rehabilitations Contract 19-015 (Commonwealth Construction)
o Contractor will begin permanent patch and repair of sidewalk panels damaged during sewer
repair work at various locations
• Sanitary Sewer Rehabilitations Contract 20-015 (Umbra & Sons Construction)
o Inland Waters will resume grouting service connections in lined sewers on Spruce Street and Mt.
Auburn Street
• 2021 Sanitary Sewer Investigations (National Water Main)
o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) and continue
flow isolation of sewers (12:00 AM — 6:00 AM) within the project area. No interruption of water
or sewer service is anticipated, however there may be temporary road closures and/or parking
restrictions.
• Sidewalk Repair Program (Century Paving)
o Contractor will continue complete streets curb and sidewalk work on Watertown Street at
Morse Street and California Street at Fifth Ave.
• Line Painting (K5 Corporation)
o NIGHT WORK —centerline and crosswalk painting, town -wide
• National Grid Gas Work
Utility companies are responsible for notifying residents prior to conducting work, but planned work
is listed below:
o Continue gas main replacement on Green Street
o Continue gas main replacement on Oak Street
o Continue gas main replacement on Beechwood Ave.
o Continue gas main replacement on Cottage Street
Note: All work is weather -dependent and subject to change.