HomeMy Public PortalAboutWeek of 0607 Work PlanAnticipated Work —Week of June 7. 2021
• 2020 Road Program & Common Street (Onyx Corporation)
o Continue curb and sidewalk on Nichols Ave.
o Begin raising structures on Nichols Ave.
o Loam and seed (project wide)
• 20-01W Water Main Replacement (Commonwealth Construction)
o Continue repair of sidewalk panels damaged during water main installation (Oak St.)
• 2021 Road Program (Lorusso Corporation)
o Finish driveway transition work, cleanup and raise castings on Gertrude Street, Goldie Street,
Elmwood Ave., and Grandview Ave.
• Sanitary Sewer Rehabilitations Contract 19-01S (Commonwealth Construction)
o Contractor will continue permanent trench repairs of impacted work areas on the following
streets:
o Belmont Street at Hardy Avenue
o Lexington Street (Highland Avenue to Bancroft Street)
o North Beacon Street (Ladd Street to Beacon Park)
o Oakley Road
o Orchard Street at Waverley Avenue
o Palfrey Street at Forest Street
o Contractor will repair sidewalk panels impacted by the work on the following streets:
o Chapman Street
o Lexington Street (Highland Avenue to Bancroft Street)
o Nyack Street
o Oakley Road
o School Street (Porter Street to Boylston Street)
• Sanitary Sewer Rehabilitations Contract 20-01S (Umbra & Sons Construction)
o Inland Waters will resume grouting service connections in lined sewers on the following streets:
o Bailey Road (Bellevue Road to Brigham Street)
o Bellevue Road (Marcia Road to Russell Avenue)
o Bridgham Avenue
o Gill Road
o Irving Street (Riverside Street to South Irving Park)
o Ladd Street
o Marcia Road
o Mt. Auburn Street (Amherst Road to Bailey Road)
o Otis Street
o Riverside Street (Perkins School to Irving Street)
o Russell Avenue (Columbia Street to Mt. Auburn Street)
o Spruce Street (Lincoln Street to Mt. Auburn Street)
o Stoneleigh Circle
o Stoneleigh Road (Stoneleigh Circle to Bailey Road)
o Walnut Street (Franklin Street to Mt. Auburn Street)
o Inland Waters will install cementitious lining in manholes on the following streets:
o Bailey Road (Brigham Street to Mt. Auburn Street)
o Garfield Street
o Harrington Street
o Holt Street
o James Street
o Mangano Court
o Marshall Street
o Riverside Street (Priest Road to Wheeler Lane)
o Russell Avenue
o Russell Street
o Washburn Street
• 2021 Sanitary Sewer Investigations (National Water Main)
o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the
Project 2 work area Note additional Proiect 3 and 4 work to begin this week as well. No
interruption of water or sewer service is anticipated, however there may be temporary road
closures and/or parking restrictions.
o Nighttime flow isolation is complete within the Project 2 work area. Flow isolation (12:00 AM —
6:00 AM) will begin within the Project 3 and 4 work area.
o Sidewalk Repair Program (Century Paving)
o Contractor will continue sidewalk repairs on Whites Ave., from Main Street to Summer Street
• Line Painting (K5 Corporation)
o NIGHT WORK —line painting, town -wide
• National Grid Gas Work
Utility companies are responsible for notifying residents prior to conducting work, but planned work
is listed below:
o Continue gas main replacement on Beechwood Ave.
o Continue gas main replacement on Cottage Street
o Begin gas main replacement on Lovell Road
o Begin gas main replacement on Arlington Street, #264 to #284 Arlington Street; Note: Mt.
Auburn Street intersection work planned on Sunday, June 6 and 13 and work (8 AM to 4 PM)
Note: All work is weather -dependent and subject to change.