HomeMy Public PortalAboutWeek of 0621 Work PlanAnticipated Work —Week of June 21. 2021 • 2020 Road Program & Common Street (Onyx Corporation) o Mill transition areas on Boylston Street at Nichols Ave., Dexter Street at Willow Park and at Nichols Ave., Kimball Road at Maplewood Street, Wheeler Lane at Riverside Street, and N. Beacon Street at Paul Street o Continue sidewalk and raised table work on Nichols Ave. o Paving date for Nichols Ave. and Wheeler Lane TBD • 2021 Road Program (Lorusso Corporation) o Binder pave Alden Road, Sheldon Road, and Hazel Street o Begin curb and sidewalk installation on Alden Road, Sheldon Road, and Hazel Street • Sanitary Sewer Rehabilitations Contract 19-01S (Commonwealth Construction) o Contractor will loam and seed on Chapman Street, Lexington Street, Nyack Street and Oakley Road • Sanitary Sewer Rehabilitations Contract 20-01S (Umbra & Sons Construction) o Inland Waters will install cementitious lining in manholes on the following streets: o Bailey Road o Bellevue Road (Bailey Road to Russell Avenue) o Burnham Street o Chandler Street o Garfield Street o Harrington Street o Holt Street o James Street o Ladd Street o Mangano Court o Marcia Road o Marshall Street o Riverside Street o Russell Avenue o Russell Street • 2021 Sanitary Sewer Investigations (National Water Main) o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the Protect 2, Project 3 and 4 work areas. No interruption of water or sewer service is anticipated, however there may be temporary road closures and/or parking restrictions. o Flow isolation (12:00 AM — 6:00 AM) will continue within the Project 3 and 4 work area. o Sidewalk Repair Program (Century Paving) o Contractor will continue sidewalk repairs on Whites Ave., from Main Street to Summer Street o Continue repairs at Town Hall and Library o Begin sidewalk repairs on Marcia Road • Line Painting (KS Corporation) o No work planned this week • National Grid Gas Work Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed below: o Continue gas main replacement on Beechwood Ave. o Continue gas main replacement on Cottage Street o Continue gas main replacement on Lovell Road o Continue gas main replacement on Arlington Street, #264 to #284 Arlington Street; Note: Mt. Auburn Street intersection work planned on Sunday, June 20 and 27 (8 AM to 4 PM) Note: All work is weather -dependent and subject to change.