HomeMy Public PortalAboutWeek of 0705 Work PlanAnticipated Work —Week of July S. 2021
• 2020 Road Program & Common Street (Onyx Corporation)
o Top course date for Nichols Ave. and Wheeler Lane TBD
o Punch list work (all work areas)
• 2021 Road Program (Lorusso Corporation)
o Continue curb and sidewalk installation on Alden Road, Sheldon Road, and Hazel Street
• Sanitary Sewer Rehabilitations Contract 19-015 (Commonwealth Construction)
o Loam and seed on Chapman Street, Lexington Street, Nyack Street and Oakley Road
o Trench repairs on Belmont Street at Hardy Ave.
• Sanitary Sewer Rehabilitations Contract 20-01S (Umbra & Sons Construction)
o Inland Waters will install cementitious lining in manholes on the following streets:
o Amherst Road
o Bailey Road
o Bellevue Road (Marcia Road to Russell Avenue)
o Belmont Street (Brookline Street to Sycamore Street)
o Bridgham Avenue
o Gill Road
o Harrington Street
o Holt Street
o Irving Street at Garnet Street
o James Street
o Ladd Street
o Mangano Court
o Marcia Road
o Marshall Street
o Mt. Auburn Street (Amherst Road to Marshall Street)
o Riverside Street
o Russell Avenue
o Russell Street
o Spruce Street (Lincoln Street to Mt. Auburn Street)
o Stoneleigh Road (Stoneleigh Circle to Bailey Road)
o Sycamore Street
• 2021 Sanitary Sewer Investigations (National Water Main)
o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the
Project 2, Project 3 and 4 work areas. No interruption of water or sewer service is anticipated,
however there may be temporary road closures and/or parking restrictions.
• Water Service Replacement Program (Paolini LLC)
o Continue water service replacement (water main to shut-off box in sidewalk) at the following
locations on Chapman Street (Warren Street to Main Street): #130/128, #122, #116/118, #114,
#109, #66, #65, #55/57, #51/53, #49, #23, and #4/6.
• Sidewalk Repair Program (Century Paving)
o Complete sidewalk repairs on York Ave.
o Begin sidewalk repairs on Garnet Street, from Irving Street to Phillips Street
• Line Painting (KS Corporation)
o NIGHT WORK —line painting, town -wide
• National Grid Gas Work
Utility companies are responsible for notifying residents prior to conducting work, but planned work
is listed below:
o Continue gas main replacement on Cottage Street
o Continue gas main replacement on Lovell Road
o Continue gas main replacement on George Street and Wilson Ave.
o No work scheduled on Arlington Street, #264 to #284 Arlington Street this week; Note: Mt.
Auburn Street intersection work planned on Sunday, July 11 (8 AM to 4 PM)
Note: All work is weather -dependent and subject to change.