HomeMy Public PortalAboutWeek of 0719 Work PlanAnticipated Work —Week of July 19. 2021 • 2020 Road Program & Common Street (Onyx Corporation) o Punch list work (all work areas) o Line painting (all work areas) • 2021 Road Program (Lorusso Corporation) o Continue curb and sidewalk installation on Alden Road, Sheldon Road, and Hazel Street o Raise castings on Alden Road, Sheldon Road, and Hazel Street o Top course paving on Alden Road, Sheldon Road, and Hazel Street • Sanitary Sewer Rehabilitations Contract 19-01S (Commonwealth Construction) Contractor will pave the following locations: o North Beacon Street at Ladd Street o Belmont Street at Hardy Avenue • Sanitary Sewer Rehabilitations Contract 20-01S (Umbra & Sons Construction) o Inland Waters will install cementitious lining in manholes on the following streets: o Amherst Road o Bailey Road o Bellevue Road (Marcia Road to Russell Avenue) o Belmont Street (Brookline Street to Sycamore Street) o Bridgham Avenue o Gill Road o Harrington Street o Holt Street o Irving Street at Garnet Street o James Street o Ladd Street o Mangano Court o Marcia Road o Marshall Street o Mt. Auburn Street (Amherst Road to Marshall Street) o Riverside Street o Russell Avenue o Russell Street o Spruce Street (Lincoln Street to Mt. Auburn Street) o Stoneleigh Road (Stoneleigh Circle to Bailey Road) o Sycamore Street • 2021 Sanitary Sewer Investigations (National Water Main) o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the Project 2, Project 3 and 4 work areas. No interruption of water or sewer service is anticipated, however there may be temporary road closures and/or parking restrictions • Water Service Replacement Program (Paolini LLC) o Continue water service replacement (water main to shut-off box in sidewalk) at the following locations on Chapman Street (Warren Street to Main Street): #49, #23, #4/6, and #180 o Begin water service replacements on Olcott St: #60, #57-59, #50, #45-47, #39, #32, #13-15, #20 o Depending on work progress, begin water service replacement at #84 King Street o Bromfield Street Water Main Replacement (Poolini LLC) o Mobilize and begin laying down water main by-pass system (carried over from last week) o Sidewalk Repair Program (Century Paving) o Complete sidewalk repairs on Garnet Street, from Irving Street to Phillips Street o Begin sidewalk repairs on Fairview Ave. • Pavement Preservation —Mill & Overlay (Lorusso Corporation) o Contractor will mill the following streets (Thursday/Friday) Auburn Court Barnard Ave. (Orchard St. to Columbia St.) Garnet St. (Irving St. to Phillips St.) Robbins Rd. (Orchard St. to Columbia St.) Spring St. (Summer St. to Palfrey St.) Washburn St. (Franklin St. to Otis St.) • Line Painting (K5 Corporation) o NIGHT WORK —line painting, town -wide • National Grid Gas Work Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed below: o Continue gas main replacement on Cottage Street o Continue gas main replacement on Lovell Road o Continue gas main replacement on George Street and Wilson Ave. o Continue gas main replacement on Arlington Street, #264 to #284 Arlington Street Note: All work is weather -dependent and subject to change.