Loading...
HomeMy Public PortalAboutWeek of 0726 Work PlanAnticipated Work —Week of July 26. 2021 • 2020 Road Program & Common Street (Onyx Corporation) o Punch list work (all work areas) • 2021 Road Program (Lorusso Corporation) o Clean up and punch list work (all streets) • Waverley Ave. Road Reconstruction (Lorusso Corporation) o Begin mobilization activities (set up tree protection, catch basin protection, etc.) • Sanitary Sewer Rehabilitations Contract 20-01S (Umbra & Sons Construction) Insituform is scheduled to install cured -in -place pipe (CIPP) on the following streets: o Franklin Street (between Center Street and Mt. Auburn Street) o Irving Street (between North and South Irving Park) o Irving Street (between Riverside Street and Fifield Street) o Webster Street (Between #39 and #60) o Perry Street (at Harrington Street) o Brigham Street (Between Garfield Street and Bailey Road) o Walnut Street (Between Center Street and Franklin Street) See 2020 Sewer Imorovements I Watertown Public Works. MA (watertowndow.om) for additional details Note: If your home or business is connected to the sewer line being rehabilitated, your sewer service will be temporarily blocked off from the sewer mainline once the liner is inflated. During this time your water service is not shut off and you can continue using it for drinking, cooking and other purposes, but residents are asked to limit water use. You should avoid taking showers or baths, running your dishwasher and washing machine, and also be sure to turn off all sump pumps connected to your sewer service. Flush your toilets sparingly. Using small amounts of water to wash your hands or brush your teeth is okay. See web -site for additional information. • 2021 Sanitary Sewer Investigations (National Water Main) o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the Protect 2, Protect 3 and 4 work areas. No interruption of water or sewer service is anticipated, however there may be temporary road closures and/or parking restrictions Water Service Replacement Program (Paolini LLC) o Continue water service replacement (water main to shut-off box in sidewalk) at the following locations on Chapman Street (Warren Street to Main Street): #180 o Continue water service replacements on Olcott St: #57-59, #39, #13-15, #20 o Continue water service replacement at #84 King Street o Begin water service replacements on Gilbert Street and Olney Street • Bromfield Street Water Main Replacement (Paolini LLC) o Chlorinate and test by-pass water system o Begin connecting buildings to by-pass system, pending testing results • Pavement Preservation —Mill & Overlay (Lorusso Corporation) • Contractor will adjust castings and top course pave: Auburn Court Barnard Ave. (Orchard St. to Columbia St.) Garnet St. (Irving St. to Phillips St.) Robbins Rd. (Orchard St. to Columbia St.) Spring St. (Summer St. to Palfrey St.) Washburn St. (Franklin St. to Otis St.) • Line Painting (K5 Corporation) o NIGHT WORK —line painting, town -wide • National Grid Gas Work Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed below: o Continue gas main replacement on Cottage Street o Continue gas main replacement on Lovell Road o Continue gas main replacement on George Street and Wilson Ave. o Note gas main replacement on Arlington Street, #264 to #284 Arlington Street, on hold pending MBTA coordination Note: All work is weather -dependent and subject to change.