HomeMy Public PortalAboutWeek of 0809 Work PlanAnticipated Work —Week of August 9, 2021 • 2020 Road Program & Common Street (Onyx Corporation) o Punch list work (all work areas) 2021 Road Program (Lorusso Corporation) o Install flexi-pave at tree pits (Grandview Ave., Gertrude St. and Hazel St.) pending material delivery • Waverley Ave. Road Reconstruction (Lorusso Corporation) o Install drain manhole near Belmont Street o Perform sewer spot repair near Lowell Street o Roadway reclamation and grading o Depending on work progress, begin base/binder pavement installation Sanitary Sewer Rehabilitations Contract 20-015 (Umbra & Sons Construction) Inland Waters is scheduled to grout service connections on the following streets: o Franklin Street (between Center Street and Mt. Auburn Street) o Irving Street (between North and South Irving Park) o Irving Street (between Riverside Street and Fifield Street) o Webster Street (Between #39 and #60) o Perry Street (at Harrington Street) o Brigham Street (Between Garfield Street and Bailey Road) o Walnut Street (Between Center Street and Lincoln Street) o Phillips Street • 2021 Sanitary Sewer Investigations (National Water Main) o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the Protect 2, Protect 3 and 4 work areas. No interruption of water or sewer service is anticipated, however there may be temporary road closures and/or parking restrictions • Water Service Replacement Program (Paolini LLC) o Continue water service replacements on Gilbert St. and Olney St. o Depending on work progress, begin water service replacements on Stuart Street, Partridge Street, Andrew Street and Gleason Street • Bromfield Street Water Main Replacement (Paolini LLC) o Begin connecting buildings to by-pass system, pending testing results • Pavement Preservation —Mill & Overlay (Lorusso Corporation) Line painting —Irving Street (NIGHT WORK) • Line Painting (K5 Corporation) o NIGHT WORK —line painting, town -wide • National Grid Gas Work Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed below: o Continue gas main replacement on Cottage Street o Continue gas main replacement on Lovell Road o Continue gas main replacement on George Street and Wilson Ave. o Note gas main replacement on Arlington Street, #264 to #284 Arlington Street, on hold pending MBTA coordination o Top course pave the Belmont Street/Duff Street intersection Note: All work is weather -dependent and subject to change.