HomeMy Public PortalAboutWeek of 0809 Work PlanAnticipated Work —Week of August 9, 2021
• 2020 Road Program & Common Street (Onyx Corporation)
o Punch list work (all work areas)
2021 Road Program (Lorusso Corporation)
o Install flexi-pave at tree pits (Grandview Ave., Gertrude St. and Hazel St.) pending material
delivery
• Waverley Ave. Road Reconstruction (Lorusso Corporation)
o Install drain manhole near Belmont Street
o Perform sewer spot repair near Lowell Street
o Roadway reclamation and grading
o Depending on work progress, begin base/binder pavement installation
Sanitary Sewer Rehabilitations Contract 20-015 (Umbra & Sons Construction)
Inland Waters is scheduled to grout service connections on the following streets:
o Franklin Street (between Center Street and Mt. Auburn Street)
o Irving Street (between North and South Irving Park)
o Irving Street (between Riverside Street and Fifield Street)
o Webster Street (Between #39 and #60)
o Perry Street (at Harrington Street)
o Brigham Street (Between Garfield Street and Bailey Road)
o Walnut Street (Between Center Street and Lincoln Street)
o Phillips Street
• 2021 Sanitary Sewer Investigations (National Water Main)
o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the
Protect 2, Protect 3 and 4 work areas. No interruption of water or sewer service is anticipated,
however there may be temporary road closures and/or parking restrictions
• Water Service Replacement Program (Paolini LLC)
o Continue water service replacements on Gilbert St. and Olney St.
o Depending on work progress, begin water service replacements on Stuart Street, Partridge
Street, Andrew Street and Gleason Street
• Bromfield Street Water Main Replacement (Paolini LLC)
o Begin connecting buildings to by-pass system, pending testing results
• Pavement Preservation —Mill & Overlay (Lorusso Corporation)
Line painting —Irving Street (NIGHT WORK)
• Line Painting (K5 Corporation)
o NIGHT WORK —line painting, town -wide
• National Grid Gas Work
Utility companies are responsible for notifying residents prior to conducting work, but planned work
is listed below:
o Continue gas main replacement on Cottage Street
o Continue gas main replacement on Lovell Road
o Continue gas main replacement on George Street and Wilson Ave.
o Note gas main replacement on Arlington Street, #264 to #284 Arlington Street, on hold pending
MBTA coordination
o Top course pave the Belmont Street/Duff Street intersection
Note: All work is weather -dependent and subject to change.