HomeMy Public PortalAboutWeek of 0907 Work PlanAnticipated Work —Week of September 7, 2021
• 2020 Road Program & Common Street (Onyx Corporation)
o Punch list work (all work areas)
• 2021 Road Program (Lorusso Corporation)
o Install flexi-pave at tree pits (Grandview Ave., Gertrude St. and Hazel St.) pending material delivery
o Punch list work (all work areas)
• Waverley Ave. Road Reconstruction (Lorusso Corporation)
o Continue curb and sidewalk installation
• Sanitary Sewer Rehabilitations Contract 20-01S (Umbra & Sons Construction)
Excel Paving will be installing permanent pavement on the following streets:
o Bailey Road (Bellevue Road to Stoneleigh Street)
o Bellevue Road (Marcia Road to Russell Avenue)
o Gill Road at Sycamore Street
o Howard Street (Acton Street to Pleasant Street)
o Marcia Road
o Perry Street at Harrington Street
o Robbins Road (Bellevue Road to dead end)
o Spruce Street (Lincoln Street to Mt. Auburn Street)
o Stoneleigh Circle
• 2021 Sanitary Sewer Investigations (National Water Main)
o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the Project 2,
Project 3 and 4 work areas. No interruption of water or sewer service is anticipated, however there may
be temporary road closures and/or parking restrictions
• Water Service Replacement Program (Paolini LLC)
o Records indicate services at #31, #84, #88, #89, #91, and #94 Rutland Street were previously replaced
and work is no longer necessary
o Begin water service replacements at #204, #148, #136, #130 and #108 Acton Street, #37, #48, #49, #66,
and #73 Buick Street, and #44 and #9 Pilgrim Road
• Bromfield Street Water Main Replacement (Paolini LLC)
o Continue water main installation
• Line Painting (K5 Corporation)
o NIGHT WORK —line painting, town -wide
• National Grid Gas Work
Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed
below:
o Continue gas main replacement on Cottage Street
o Continue gas main replacement on Lovell Road
o Continue gas main replacement on George Street and Wilson Ave.
o Note gas main replacement on Arlington Street, #264 to #284 Arlington Street, on hold pending MBTA
coordination
Note: All work is weather -dependent and subject to change.