HomeMy Public PortalAboutWeek of 0920 Work PlanAnticipated Work —Week of September 20, 2021
• 2020 Road Program & Common Street (Onyx Corporation)
o Punch list work (all work areas)
• 2021 Road Program (Lorusso Corporation)
o Install flexi-pave at tree pits (Grandview Ave., Gertrude St. and Hazel St.) pending material delivery
o Punch list work (all work areas)
• Waverley Ave. Road Reconstruction (Lorusso Corporation)
o Continue curb and sidewalk installation
• Sanitary Sewer Rehabilitations Contract 20-01S (Umbra & Sons Construction)
o Replace sidewalk panels damaged as part of the sewer/drain reconstruction on Robbins Road Extension
• 2021 Sanitary Sewer Investigations (National Water Main)
o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the Protect 2,
Protect 3 and 4 work areas. No interruption of water or sewer service is anticipated, however there may
be temporary road closures and/or parking restrictions
• Water Service Replacement Program (Paolini LLC)
o Continue water service replacements at #204, #148, #136, #130 and #108 Acton Street, #37, #48, #49,
#66, and #73 Buick Street, and #44 and #9 Pilgrim Road
o Depending on work progress, begin water services at #8, #12, #16-18, #24-26, #45-47 Oakland Street;
#23-25, #27-29 Morton Street; and #17-19 Howard Street
• Bromfield Street Water Main Replacement (Paolini LLC)
o Test and chlorinate water main between Acton and Nash Street
o Based on testing results, begin services between Acton Street and Nash Street
• Sidewalk Rehabilitation (Century Paving)
o Continue sidewalk repairs on Yukon Ave. and at #25 Bigelow Ave.
o Depending on work progress, begin sidewalk repairs on Bailey Road
• Line Painting (K5 Corporation)
o NIGHT WORK —line painting, town -wide
• National Grid Gas Work
Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed
below:
o Continue gas main replacement on Cottage Street
o Continue gas main replacement on Lovell Road
o Continue gas main replacement on George Street and Wilson Ave.